Tag Archives: God

Homestead update: not a lot of progress in the last two months

So, last I wrote about the house, we were still waiting on contractors to come finish the siding and roof. Our house sat with only 1½ walls for 4 months till the new contractors finally fit us into their schedule. They finally started and I jumped in to help on a particularly windy day. In the process of helping, I learned how to do it.

So when some unavoidable delays happened again, we decided to take matters into our own hands.

Brushing off the dirt from the panels

And there were were, a family of rock stars who put the preliminary insulation, and siding up on 1½ of our walls, all by ourselves.

But then…

Before the contractors could come back and start on the roof, there was some trim work that needed to be done. And we REALLY wanted that roof. So, we continued working sun up to sun down in a push to get ready for the contractors.

With the help of some good friends

This picture makes me so happy. I love that my girl is old enough to be a huge help, but also to really remember this awesome adventure we get to have as a family.

We got the trim all on and it was time for the roof.

But first…

Yep, that’s a fire pit. INSIDE our house. How many of you can say you’ve done that?

And then the day finally came that the roof started going on!

Oh Happy day!

Pajii got to help!

Finally! The roof was on, but there was still a bit of trim work to do before we no longer had the equipment. So once again, my brother and sis-in-law jumped in to help out.

And then it was done, done!

We still have to cut in the doors and windows, but at least it’s “dried in”.

So the exterior structure of our house was done. And so was I!

This is what happens when you hurt your knee but don’t really take the time to slow down and heal. It keeps getting worse until it’s so bad you can’t walk on it any more!

So, I was laid up for about a week, waiting for my knee to heal well enough that I could get back to work.

But in the meantime, we had one more job to do with that equipment.

Putting in our cistern tank.

But let me back up…

Last summer, we needed to rent a large excavator to widen our garage pad. We also dug the hole and trench for our cistern system (say that three times fast!). A cistern is a fancy way of saying a water tank. This one is specifically a holding tank that we will fill with our well water and use as the water for our house. Being off grid, this is the best system.

But in order to get the tank in the hole, we needed to prep the hole and run the line for the water.

Remember the part I said the hole and trench were dug last year?

Yeah, it wasn’t pretty. And this picture is after Pajii had cleared all the big rocks out! But that entire trench had to be bedded in sand for the pipe to lay on. And how do you get dirt up a 175 foot long trench that is 3+ feet deep and only 2 feet wide?

With buckets. Lots and lots (and lots and lots) of buckets full of sand! In fact, that’s how I hurt my knee, all the way back at the beginning of June. Carrying those heavy buckets (each one weighs roughly 40lbs when full!)

And where were we getting the sand for most of the job?

From our own sand pit, of course. We bedded and covered nearly a hundred feet of pipe on a very steep hillside by “mining” sand from our property. A lot of extra work, but it was free, and we had the time (we were still waiting for the contractors at the point.)

So fast forward several weeks. The contractors came and went and we had abandoned the trench prep in lieu of working on the house (because, priorities), I had begun to heal from my knee injury, and we were looking forward to finishing the cistern and starting the next phase of the journey.

But that was not God’s plan. My Dad’s health took a drastic turn for the worse and it became apparent that he should no longer be living alone, and therefore, his house on the other end of town needed to be sold. So, very reminiscent of when we dropped everything and moved to Oregon in 2014 to care for Hub’s ailing mom, we dropped nearly everything to care for my ailing dad and get his house ready to sell.

That was at the end of June. It took two months, but I’m happy to say, PopPop is now settled in here with us (in his own trailer), his house is in escrow, and we only have one more load to bring home from his house.

But in the midst of all that, we needed to finish the cistern. And we needed to do it quick. We had already put in so much work to it, that to leave it at the mercy of the elements was just stupid. So, while we still had the equipment we used for the siding on the house, we put in the cistern. Then we had to bring in load after load of DG (saving us the time and effort of shoveling it from our own property). But, how do you get the DG from the trailer on the road, down 15+ feet to the hole that the cistern is in?

That’s right, some of our roofing and siding scraps. The sand just slid right in. Quite ingenious, if I do say so myself.

And so easy, a 5 year old could do it.

Then it was another while before we could get it finished. That entailed hooking up the supply pipes, etc to the tank.

Hubs is inside the tank, putting holes in it!

Starting to fill in the hole to cover the tank

And that brings us up pretty much to the present. Here’s an updated picture of the dianthus bush I planted.

The dianthus has not done too well in our hot summer, but the alyssum, petunias, zinnias, and marigolds that I planted around it have just about taken over!

And we’ve got another broody hen who has been sitting on golf balls for 5 days. I put 9 fertile eggs under her this evening. This will be hen #6 that we’ve tried to get to set till the eggs hatch. It has been misadventure after misadventure. But I’ve learned a lot and have great hopes that this clutch of eggs will be the one!

We did have two chicks hatch from our very first broody hen of the season.

I’m not sure why only two of the 7 eggs survived. Of those other 5 eggs, one chick was half hatched, three were fully formed as far as I could tell but had died before hatching, and one had gone rotten from the beginning of the brood. But I was totally excited to get two of our very own, completely home grown chicks! Too bad they both turned out to be boys. 🙄😒

And now, for the truly, truly up-to-date update:

We’ve started working on the Septic System: Phase 2! By the end of the week, we should have a complete septic system. Hallelujah!

Using a friend’s transit level to lay out the septic field.

The middle one of the three required leach lines marked out.

And today, we started cutting the trenches. But that’s another post for another time. Right now, I am t-i-r-e-d. And we still have at least another two hard days of work till we can call for inspection.

Nighty night. Don’t work too hard!

House update: getting ready for concrete

We are scheduled for our slab pour in just two days! (“Lord willing and the creek don’t rise.”)

Its been a lot of hard work getting to this point where we are ready to pour (and there’s still some work to be done tomorrow.)

When I last updated, we had just started cutting the trenches for the plumbing and footers.

This looks like a complete disaster, but there really is some order to it.

This is the same area later that same day.

We put a call for help out on Facebook and a bunch of our extended family showed up to help with the shoveling.

Even Flower Girl was a huge help!

My brother manning the sifting station.

My sis-in-law lugging some buckets of dirt out of the forms.

We were able to dig nice and neat trenches for the interior footers.

Once we got the trenches all dug and cleaned out, it was time to start on the drain piping.

ABS fittings

Our first completed branch line dry-fitted.

Once we had all the pipes laid out where and how they needed to go, we had a few days wait for our retired contractor friend to stop by and let us know how we did. He made a few suggestions which we followed.

While we waited for him, we made a good start on our septic system.

When we got the go ahead from our friend, we started gluing all the drain pipes and fittings together.

And bedding all the pipes in sand.

The girls had fun talking to each other through the pipes.

Then we had to test the system. This involved capping off all the pipes except this really tall one, then filling the whole system with water.

We only had the backhoe for a limited amount of time, so we got as much done with it as we could. Such as getting the water line put in across the driveway.

This line will eventually connect to an underground cistern which we will fill from our well pump.

I let Princess Girl try her hand at moving the backhoe around (with me right next to her, of course.)

We passed our under-slab plumbing inspection, and it was time to start backfilling. Again.

This time we needed to use sand to completely cover the pipes.

A good friend came by to lend a hand.

Flower Girl love playing in the sand.

She also found a way to go sledding in September. 😄

Once we had the sand over the pipes, we switched to using type 2 base and we were back to filling and compacting.

Once the pad was fully backfilled, there was just once last project to do with the backhoe before we had to turn it back in to the rental company. We needed to cut our footers for our garage and the trench across the drive to run electrical lines.

Then it was time for rebar!

Over the next several days we worked to get all the rebar finished in time for our inspection. We hit a couple delays, but managed to git ‘er done.

And that brings us up to our current situation. We had our inspection on Monday and passed with flying colors. Our concrete contractor was booked up till Friday, so that’s when we’re scheduled. We still have a couple odds and ends to take care of before we pour on Friday, so we’ll be taking care of those tomorrow.

So, Lord willing, we’ll have a finished slab by Friday evening! And let me tell you, it’s none too soon. The temps are dropping and freezing weather is just around the corner.

We’ve worked hard, but it’s exciting to see the progress. Hopefully when I update next the slab will be done!

Even more weather related delays

So, it rained a couple days ago, causing us to button down the hatches and close up shop early. We ended up spending a rare evening together just hanging out. It was great.

But the next day we decided to hit it hard and get some actual work done.

In the morning Flower Girl and I worked on marking out our under-slab plumbing.

First I made a copy of our plans so that I could mark on them.

Then we started transferring the measurements to the ground with paint.

This four year old’s got some skills!

After a trip to take Pajii to a doctor appointment, we were back at it.

It was nice that for this phase, the measurements don’t have to be exact. That will come next as we are laying the pipe.

For now, we will cut our plumbing trenches with the backhoe since that’s what we have. We are not going to rent something else when we already have something that will work. So our trenches will be wider than absolutely necessary. But then again, they are gonna be pretty deep, so we need room to maneuver around in them with the pipes, so maybe it will be fine. All that to say that we don’t have to be very precise with our measurements at this stage because the trenches will be wide enough for some adjustment of the placement of the pipes. Whew!

Just two tools needed for this job. Nice to not have to lug around a bunch of heavy tools.

Consult the Book of the House. Chapter 2 verse 3, “Thou shalt mark thy plumbing upon the subfill with the paint color of thy choosing providing thou doth chooseth a color which doth show brightly upon the ground.”

We got the lines all drawn. Red for plumbing and orange for interior footers.

We excitedly started destroying some of our hard work that we put into compacting all that dirt. And then this happened:

Yes, that’s rain and hail, and Princess Girl and I were stuck inside the backhoe. Thankfully it is an enclosed one so we had good protection and didn’t have to try to make a mad dash through this:

So, again, we were stopped from working by the weather.

This morning, I went out to start back up again and found this:

That’s one big soupy mess, right in the middle of our house. So I decided to let it dry out some and work on one of our other projects that need to get done while we have the backhoe.

So I cleaned out the drainage next to a potion of our driveway. It’s kinda hard to see, but there wasn’t a real ditch here before I started. The water would run down the side and the middle of the road and eventually spread across the drive near the highway, leaving all the mud as a parting gift as it found an edge on the other side and headed on down the canyon.

Flower Girl helped move rocks for a time, then started pretending she was a prairie dog. I just love her imagination.

By 2:30, we were done with the drainage for the day (still need to put in a culvert pipe). The girls and their grandfather were preparing to head off to gymnastics class, and I headed in town to run an errand and hoped that the sun would continue to dry out the pad.

When I got back and Hubby was home from work, we still had several hours of light left, so we decided to try working on the pad despite the remaining puddles of water.

I was amazed at how hard it was to dig by hand through the compacted dirt. Guess we did a good job compacting it.

Hubby worked on digging down to where our sewer pipe will exit the building (pictured above), while I worked on unearthing the rebar that will join into the footer for the interior load bearing wall.

I am well please at how well this backfill is staying neat and tidy as we dig. That’s exactly what we were hoping for. Now, if the rain will just stay away long enough for us to get the slab poured, that would be amazing!

You know what else is amazing? One of Pajii’s kittens, Lilly.

She’s so cuddly. And just look at that face! Almost makes me want another cat. Almost. But not quite. Maybe when we have a barn and they can be barn cats. Maybe we’ll get some kittens then. For now, I enjoy playing with Lilly and Midnight whenever I’m in Pajii’s trailer.

So anyway, that’s our last few days. The rain has put a damper on our progress a bit, but it also means we get some of these other important projects done as well.

And that’s how life goes. God’s got a plan for everything. We just have to trust that he knows what he’s doing.

Change of plans

First, we had to delay starting our house because we had to move to Portland for almost 2 years to help care for the Hubby’s mom. 

We ended up needing to plan a bigger house than we originally thought in order to accommodate Hubby’s folks moving in with us.

Then we had to completely move the location of the house from one side of our 40 acre property to the other because the original site didn’t have a good spot for septic.

We planned to get more work done over the winter, but the weather did not cooperate.

And here we are, having to change some of our house plans. 

Yet again.

Plotting the original corner of the house

It wasn’t a major change, we just changed the directional orientation of the house a few degrees. It amounted to moving the house about 15ft. Not that big of a deal, except that it really cuts down on the amount of driveway and parking area we’ll have. It was just feeling…Well, cramped. 
And yes, we do have 40 acres, but only about 3 of those are not on the side of a steep hill. And the house pad is carved out of the side of one of those hills. So we are kinda limited on space in some ways. 

But I digress. Since we changed the angle of the house, we had to look at where the detached garage is going to be built and how to get more space.

Which made us consider doing some earth moving in a area where we planned to put our orchard.

Which would give us much more space on the house pad, but where to put the orchard instead? 

Which made us look around and decide that the other logical place for the orchard is actually better. 

Which made us realize once again that when plans have to change for one reason or another, there’s usually a silver lining. I could go down the list at the beginning of this post and show how  because we had to do it differently than originally planned, we’re actually better off now than we would have been had our original plans gone through. 

In the Bible, James tells us that when we make our plans we need to realize that God is the one who is ultimately in control and we can only follow through with our plans if it is his will (James 4;13-15). Similarly, Proverbs 19:21 says, “Many are the plans in a man’s heart, but it is the Lord’s purpose that prevails.”

We try to remember these truths when making our plans, and realizing that when plans change, it’s all for the best, in one way or another.